Grays Town Deal Programme - Project 4: Grays Beach Park & Kilverts Field and Project 5: Riverfront Activities Centre
Project 4: Grays Beach Park & Kilverts Field - Destination Attraction
Aims to embrace the natural uses of the riverfront further by connecting existing open spaces (Grays Beach Riverside Park and Kilverts Field) and the riverfront.
Enhancement of the riverfront and connectivity with the river includes the provision of physical events space and infrastructure, small multi-use structures, space for community-led public arts projects, and the reconfiguration of the Lightship Café to provide an improved food and beverage offer enabling the provision of intergenerational activities all year round.
Project 5: Riverfront Activities Centre
The Riverside Activities Centre seeks to establish a strong sense of place with the riverfront connecting with Grays’s maritime identity, history, and culture.
Progress
In December 2024, a Project Adjustment Request to amalgamate Project 4: Grays Beach Riverside Park & Kilverts Field - Destination Attraction and Project 5: Riverfront Activities Centre into a single initiative was submitted MHCLG for approval.
Merging the Café (from Project 4) with the Activities Centre (from Project 5) into a single building brings numerous advantages, particularly in terms of operational efficiency and long-term business viability.
By consolidating both facilities under one roof, operational costs are reduced, enabling more streamlined management and bolstering financial sustainability. This synergy creates a dynamic and vibrant atmosphere that fosters continuous engagement, drawing visitors throughout the day and into the evening. The café would complement the recreational offerings of the Activities Centre, forming a welcoming, multi-functional space that supports various events and gatherings.
Situated along the riverfront, this integrated approach enhances the area’s identity, boosting its appeal and solidifying its role as a central hub for recreation. Moreover, the co-location of these facilities maximises regeneration opportunities, furthering the Town’s broader goals for growth and community engagement.
Indicative Timescales
Spring 2025 | Secure Building Operator |
Autumn 2025 | Design Development |
Winter 2025 | Planning Submission |
Spring 2026 | Procurement of Building Contractor |
Summer 2026 | Commencement on Site |
Summer 2027 | Completion |